Contingency Reserve vs Management Reserve: Key Differences

Published
23rd Apr, 2024
Views
view count loader
Read it in
10 Mins
In this article
    Contingency Reserve vs Management Reserve: Key Differences

    Around 18-19 years back, when I created my first complete and exhaustive project plan independently, I was confident that my team could execute the project successfully without any challenges. It doesn't take much to know that I soon learned of my naivete. I quickly understood why Helmuth von Moltke said that "no plan survives contact with the enemy." My efforts to find the techniques to manage such project risks and challenges that have the potential to derail the entire project brought me to an understanding of contingency and management reserves. I will share those techniques with you in this article, which describes the key differences between contingency reserve vs management reserve.

    At a high level, to give you an example, consider a ship sailing for a long voyage. Would it ever sail without lifejackets, lifeboats, and additional food and water that can help in mid-sea accidents or unforeseen delays? Contingency reserves and management reserves are your lifeboats and extra food and water. Of course, there are significant differences between the two, and we will see them all and other aspects in detail. These topics are also explained in detail due to their importance in all Project Management training courses.

    What is a Contingency Reserve?

    When you perform Project Risk Management, you identify potential risks and the probability and impact of each of those risks. Based on this analysis, you build buffers to mitigate such "Known Unknown" risks.

    The buffers or reserves you include in your project plans are called "Contingency Reserves." They are the safety nets for your project, designed to absorb the impact of risks identified and quantified as part of your risk analysis processes.

    If we extend our earlier analogy, contingency reserves in project management are like life jackets on the ship. You stock those depending on the number of people on the boat.

    What is a Management Reserve?

    On the other hand, there will always be "Unknown Unknowns" or unidentified risks for your projects. These are the risks that are difficult or impossible to identify and quantify beforehand. Yet, they may realize and impact your project outcomes. Hence, management, typically beyond the horizons of the project management team, allocates a predefined percentage of resources as a buffer for such unforeseen risks. These buffers are called Management Reserves.

    Extending our earlier analogy, management reserves are like extra food on the ship. The number of people and the length of the voyage will influence it, but it doesn't have a one-to-one relation with either of those.

    Understanding both reserves is crucial if you are taking a PMP certification course and planning to appear for the exam.

    Contingency Reserve vs Management Reserve: Comparison Table

    Now, let us overview the critical difference between a contingency reserve and a management reserve.

    Parameter

    Contingency Reserve

    Management Reserve

    Authority

    Controlled by the Project Manager/Project Management Team

    Controlled by Senior Management, out of the project team's control

    Visibility

    Transparent to the project team

    Unknown to the project team

    Objective

    Mitigate and respond to known (identified and quantified) risks – to address known unknowns

    Respond to unforeseen risks – to address unknown unknowns

    Part of Project Baseline

    Yes

    No

    Flexibility of Use

    For specific identified risks

    It can be used for any unforeseen situation

    Purpose

    Linked to specific risks

    Addresses major unforeseen events

    Calculation

    Based on Risk Probability & Impact

    Usually, a percentage of the total project budget/schedule

    Difference Between Contingency Reserve vs Management Reserve

    While the table above provides a high-level overview of contingency reserve vs management reserve differences, let us now see more details. Understanding these details is critical if you plan for PRINCE2 Foundation and Practitioner certification, as they are crucial to project controls.
     

    1. Contingency Reserve vs Management Reserve: How do You Manage

    Though contingency reserves are calculated initially, good project managers proactively manage them throughout the project. They regularly revisit and reassess the contingency reserves as the risk profile changes during the project. Such an iterative approach will allow you to ensure that your contingency plan is aligned with the overall project environment. Proactive communication with the team and stakeholders will help a more coordinated response in the event of risk realization.

    Clear and continuous communication is also crucial for managing management reserves since the senior management controls these. You must provide timely updates on the progress of the evolving project and potential challenges. The visibility allows management to make informed decisions about utilizing management reserves for risk response.

    2. Contingency Reserve vs Management Reserve: Benefits

    Contingency Reserve:

    • Contingency Reserves act as a proactive measure to mitigate known risks, providing a safety net for the project team.
    • Immediate availability of resources allows the project team to respond swiftly to emerging challenges, maintaining project agility.
    • A clear link with risks enables project managers to proactively respond to risks while balancing resource availability.

    Management Reserve:

    • Management Reserves enable senior management to address significant unforeseen changes or adjustments, helping retain strategic flexibility to respond to challenges.
    • Management Reserves ensure that significant decisions align with the overall organizational strategy.
    • The undisclosed nature of Management Reserves allows for confidential decision-making at the senior management level, thus helping with efficient resource utilization.

    3. Contingency Reserve vs Management Reserve: challenges

    Contingency Reserve:

    • There is a risk of overestimating potential challenges, leading to allocating excessive resources to Contingency Reserves.
    • It might be challenging to balance allocating enough resources for contingencies without compromising the project's budget, timelines, and other constraints.

    Management Reserve:

    • The need for approval from senior management may introduce delays in responding to urgent project needs.
    • Since the management reserves are not visible to the project team, it can lead to communication gaps, as team members may be unaware of the available resources. This lack of visibility may result in inefficient or ineffective risk response.

    4. Contingency Reserve vs Management Reserve: How to Calculate?

    Contingency Reserves

    Calculating Contingency Reserves involves a systematic risk analysis process. Quantitative risk analysis techniques can be used to estimate the potential impact and probability of identified risks. You can calculate the reserves required based on the accepted risk response strategy. The calculated contingency amount is then added to the project baseline, ensuring that resources are allocated to address anticipated challenges.

    There are a few methods that I have seen being used to calculate contingency reserves. The primary one is the Expected Monitory Value (EMV) technique. This statistical technique helps calculate the expected value of a particular risk. It involves multiplying the probability of occurrence by the impact. For example:

    Suppose you identify four risks with probabilities and impacts as follows:

    • Risk 1: 20% probability, -$5,000 impact
    • Risk 2: 40% probability, -$2,000 impact
    • Risk 3: 15% probability, +$3,000 impact
    • Risk 4: 55% probability, -$1,500 impact

    Calculate the EMV for each risk: EMV = (Probability) × (Impact)

    • EMV for Risk 1 = 20% × (-$5,000) = -$1,000
    • EMV for Risk 2 = 40% × (-$2,000) = -$800
    • EMV for Risk 3 = 15% × $3,000 = $450
    • EMV for Risk 4 = 55% × (-$1,500) = -$825

    Total EMV = -$2,175

    The organization would need to allocate $2,175 to cover all identified risks.

    The other methods you can use are Decision Tree and Monte Carlo Simulation. KnowledgeHut's best Project Management training covers these areas in more detail.

    Management Reserves

    At senior management's discretion, Management Reserves may not have a precise calculation method. Instead, senior management considers the overall organizational strategy, potential impacts on the business, and the level of uncertainty in the project. This subjective approach allows for strategic decision-making at the higher levels of the organization. The reserves are typically allocated as a percentage of the project budget.

    For example, imagine a software development project with a $1 million budget and a 20% management reserve. This translates to a $200,000 buffer for unforeseen situations. If any such situation arises, you might use some of this reserve to implement the risk response without derailing the project.

    5. Contingency Reserve vs Management Reserve: Example

    Consider a SaaS development project where the project team has identified the risk of employee churn impacting the timeline. The project manager allocates a Contingency Reserve of additional costs to hire a temporary team member to accommodate potential delays due to a team member suddenly leaving. This reserve is transparently communicated within the project team, allowing for a coordinated response if adverse weather conditions materialize.

    Now, imagine a situation where unexpected changes in industry regulations are introduced, requiring a significant project redesign from a compliance perspective. In this scenario, senior management activates the Management Reserve to allocate additional funds and resources for the redesign. The utilization of Management Reserves is discreet, with information selectively communicated to key stakeholders to prevent unnecessary concerns within the project team.

    6. Contingency Reserve vs Management Reserve: methodology

    The methodology for Contingency Reserves revolves around identifying, analyzing, and mitigating risks. This includes:

    • Risk Identification: Systematically identify potential risks that could impact the project.
    • Risk Analysis: Assess the impact and probability of identified risks using quantitative or qualitative methods.
    • Risk Response: Develop strategies to define risk response, including allocating Contingency Reserves.
    • Monitoring: Regularly monitor the project landscape for emerging risks and reassess the contingency plan as needed.

    Management Reserves, being more strategic, involve:

    • Strategic Alignment: Ensure that decisions regarding Management Reserves align with the overall organizational strategy.
    • Decision-Making: Senior management makes decisions on utilizing Management Reserves based on the project's impact on the business.
    • Communication: Establish clear communication channels between project managers and senior management to facilitate timely decision-making.
    • Oversight: Provide strategic oversight to ensure that Management Reserves are utilized judiciously and aligned with organizational goals.

    7. Contingency Reserve vs Management Reserve: Calculation

    Contingency Reserve: Stakeholders, including project team members and relevant external parties, are actively involved in identifying and analyzing risks. Their insights contribute to a comprehensive understanding of potential challenges, and their buy-in is crucial for successfully implementing risk response strategies.

    Management Reserve: Stakeholder involvement in Management Reserves is limited, primarily involving senior management and key decision-makers. The strategic nature of Management Reserves often requires a more discreet decision-making process, with input from stakeholders kept at a need-to-know level to prevent unnecessary concerns.

    How are They Similar?

    While management reserves and contingency reserves differ significantly in multiple aspects, they share common ground in many others:

    1. Risk Management: Both reserves aim to manage risks and ensure project success. Contingency Reserves specifically target known risks, while Management Reserves address a broader spectrum of unknowns, allowing for a more comprehensive risk management approach.
    2. Resource Allocation: Both reserves involve allocating additional resources to address unforeseen challenges during the project lifecycle. These resources can include extra time, budget, or personnel, ensuring the project team is well-equipped to handle unexpected situations and maintain project progress.
    3. Strategic Impact: Both reserves play a crucial role in the strategic success of a project. Contingency Reserves provide the project team with the necessary support to navigate anticipated challenges, minimize disruptions, and meet project objectives. On the other hand, Management Reserves offer senior management the flexibility to respond strategically to significant changes, allowing for effective adaptation and alignment with the project's overall goals.
    4. Project adaptability: Having these reserves fosters agility and the ability to adjust course effectively when needed.
    5. Data-driven decision-making: Both require careful analysis of risks, budget, and project complexity to determine appropriate amounts.

    Thus, while Contingency Reserves and Management Reserves have distinct purposes, they contribute to effective risk management, resource allocation, and strategic decision-making, ultimately enhancing the overall success of a project.

    What Should You Choose Between Contingency Reserve and Management Reserve?

    The choice of Contingency Reserve or Management Reserve depends on various factors and the project's nature. Here are a few points I would recommend for upcoming and early-stage project managers seeking clarity:

    1. Project Complexity: For projects with a higher level of complexity and uncertainty, combining both Contingency and Management Reserves may be beneficial. Contingency Reserves address known risks, while Management Reserves provide a safety net for the unknown.
    2. Organizational Culture: Consider the organizational culture and the level of transparency desired. If the culture values open communication and collaboration, emphasizing Contingency Reserves may be more suitable. However, in organizations where strategic decision-making is closely guarded, Management Reserves may align better.
    3. Risk Appetite: Evaluate the risk appetite of the organization. If there's a higher tolerance for risk and a preference for decentralized decision-making, Contingency Reserves may be favored. Conversely, if the organization prefers a more centralized and strategic approach to risk management, Management Reserves may be the preferred choice.

    Instead of approaching the choice as an either/or exercise, the key is to understand the nuances of each of the contingency and management reserves for project management and leverage them strategically based on your project's unique needs.

    Conclusion

    Risk management becomes crucial for project managers in highly complex and uncertain environments. We must grasp the nuances of each reserve to navigate the uncertainties ahead so we can make decisions appropriately regarding contingency reserve vs management reserve. The judicious use of Contingency Reserves empowers project teams to confront known risks head-on, fostering a culture of transparency and collaboration.

    Meanwhile, the strategic deployment of Management Reserves allows senior management to steer the ship through uncharted waters. As you embark on your project management journey, reflect on the delicate balance between control and flexibility, transparency, and confidentiality. By understanding the tradeoffs between contingency reserve versus management reserve, you can chart the course for your projects, ensuring they sail smoothly even when storms of uncertainty loom on the horizon.

    The primary keyword is a bit odd for conversational purposes. I have added it as is here to comply with guidelines and requirements. Let me know if I can change it more appropriately, though that will take a different form than the exact keyword.


    Frequently Asked Questions (FAQs)

    1In what scenarios is the management reserve typically used?

    The Management Reserve is typically deployed in specific scenarios that involve significant unforeseen changes, adjustments, or strategic shifts within a project, i.e., towards situations that are unknown to the project team. Such unexpected changes may include regulations or market conditions, resource availability changes, or technological advancements or opportunities, like implementing more efficient technology or processes or investing in strategic aspects to improve the project outcomes further.

    2Are contingency reserves included in the project budget, and how are they accounted for?

    Contingency reserves are part of the project budget. They are allocated to the risks identified at the activity and work package levels. Every work package is assigned to a control account for budgeting and cost-tracking purposes. Contingency reserves decrease over time as the events or activities associated with the risk are complete and no longer valid.

    3How does the use of management reserve impact the overall project budget and timeline?

    Utilizing the management reserve typically doesn't directly impact the initial project budget or timeline. However, if unforeseen events necessitate its use, it can lead to budget adjustments to accommodate additional costs and potentially extend the timeline depending on the nature of the situation.

    4How are contingency and management reserves reflected in risk management planning?

    Contingency reserves are explicitly allocated in response to identified risks during the planning phase, serving as a proactive buffer against anticipated uncertainties. Management reserves, while not explicitly detailed in risk management planning, act as a strategic backstop for unforeseen and significant changes, allowing for agility in responding to unknown unknowns. Both reserves demonstrate proactive planning and preparedness, contributing to a robust risk management strategy.

    5What are the best practices for managing and reporting on these reserves during a project?

    Following are some of the best practices for managing and reporting the reserves:

    Track usage and remaining balance.

    Document justification for reserve expenditure.

    Communicate status to stakeholders regularly.

    Review and update reserves as needed.

    Maintain transparency and avoid misuse.

    Following these practices ensures responsible management and fosters trust in your risk management approach.


    Profile

    Kevin D.Davis

    Blog Author

    Kevin D. Davis is a seasoned and results-driven Program/Project Management Professional with a Master's Certificate in Advanced Project Management. With expertise in leading multi-million dollar projects, strategic planning, and sales operations, Kevin excels in maximizing solutions and building business cases. He possesses a deep understanding of methodologies such as PMBOK, Lean Six Sigma, and TQM to achieve business/technology alignment. With over 100 instructional training sessions and extensive experience as a PMP Exam Prep Instructor at KnowledgeHut, Kevin has a proven track record in project management training and consulting. His expertise has helped in driving successful project outcomes and fostering organizational growth.

    Share This Article
    Ready to Master the Skills that Drive Your Career?

    Avail your free 1:1 mentorship session.

    Select
    Your Message (Optional)

    Upcoming Project Management Batches & Dates

    NameDateFeeKnow more
    Course advisor icon
    Offer
    Whatsapp/Chat icon