Being a Project Manager, I wanted to write this article to share my professional experience of working on probability and impact matrix. Before getting into the core subject, let me explain to you about Qualitative Risk Analysis since risk probability impact assessment is one of the tools and techniques of Qualitative Risk Analysis.
Qualitative Risk Analysis is simply the process of prioritizing the risk based on probability of occurrence and impact, as well as other characteristics. This assists in ranking project risks by assessing their probability of occurrence and the magnitude of their potential consequences. I recommend all my mentees who are preparing for PMP certification to take Project Management certification online courses.
What is Probability and Impact Matrix in PMP?
If you are preparing for the Project Management Professional (PMP)® exam, then you need to know about RISK impact and probability matrix.
A probability and impact matrix - a tool used in qualitative risk analysis to evaluate the probability and impact of identified risks.
PMBOK® Guide seventh edition definition of probability and impact matrix:Grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs also known as risk probability and impact matrix.
Difference Between Probability and Impact Matrix
Probability
Impact
How likely the risk is to occur
What would happen if the risk materialized
Discoverability
Reproducibility
Exploitability
Affected users
Damage Potential
Uncertainty Dimension
Effect Dimension
Very Low probability – not worth considering
Very low impact – not significant to project
Low Probability – unlikely to occur
Low impact – can be managed without mitigation
Medium probability – realistic chance of occurrence
Medium impact – may require mitigation
High probability – likely to occur
High impact – significant impact on cost / schedule
Very high probability – almost certain to occur
Very high impact – can be a “project killer”
Let me give you simple illustrations as an example to understand better about Probability and Impact:
Goat 1: When I glance into the journey of Goat 1, I can focus on the hurdle or risk which is in the form of pothole filled with water. The probability of the goat getting into the pothole is low since it’s very small and even if it happens impact will be zero or Low since it’s not deep and filled just the water.
Goat 2: When I glance into the journey of Goat 2, I can focus on the hurdle or risk which is in the form of a big wide hole filled with water. The probability of the goat getting into this hole is High since it’s very wide and if it happens impact will be Low since it’s not deep and filled with water.
Goat 3: When I glance into the journey of Goat 3, I can focus on the hurdle or risk which is in the form of a small and deep hole with sharp objects. The probability of the goat getting into this hurdle is Low since it’s not wide but if it happens impact will be high since deep in the hole, sharp-edged material is placed which can cause serious injury to the goat.
Goat 4: When I glance into the journey of Goat 4, I can focus on the hurdle or risk which is in the form of a big, wide, and deep hole with sharp objects. The probability of the goat getting into this hurdle is high since it’s wide. If it happens, the impact will also be high since deep in the hole, sharp-edged material is in place which can cause serious injury to the goat.
How To Identify Risks?
PMBOK® Guide provides a clear methodology for the identification of risk– the actual process of identification as described lacks any internal structure. There are several ways to identify the risk: SWOT (Strength, Weaknesses, Opportunities, and Threats) analysis, Root Cause Analysis (RCA), Affinity Diagram (KJ diagram), Brainstorming, Interviews, Checklists and Nominal Group Technique (NGT).
I would like to discuss four helpful ways in which I identify the risks in all my projects
SWOT analysis
Root cause analysis (RCA),
Brainstorming
Affinity Diagram (KJ Diagram),
This will help you understand my suggestions in detail. I would also like to suggest my readers take Project Management Professional course which can be a great way to enhance their career.
SWOT Analysis: SWOT stands for Strengths, Weaknesses, Opportunities, and Threats. It is a framework that helps to assess and understand the internal (Strengths and Weaknesses) and external (Opportunities and Threats) factors that may create opportunities or risks for the project.
Root Cause Analysis (RCA): A set of problem-solving techniques and tools that offers project managers an opportunity to identify the root cause of the problem.
Brainstorming: It is one of the key methods of ideation, the process of generating many innovative ideas. Gathering project team members to think and discuss the project to identify the potential risks can help significantly.
Affinity Diagram (KJ diagram): Tool that gathers large amounts of data (ideas, issues) and grouping them based on their similarities. Project team members will write potential risk and group them under the buckets of finance, safety, operations etc.
How to Calculate Probability and Impact Matrix?
To calculate the probability and impact matrix, here are the suggested 4 steps you can follow:
Step 1: Identify the risk related to the project.
Step 2: Define and determine risk criteria for the project.
Step 3: Analyze the risks identified.
Step 4: Prioritize the risk and create an action plan.
A. Probability (Likelihood): X- axis pertains to how likely it is for the risk to occur.
Rare: unlikely to happen and/or have minor or negligible effect.
Unlikely: possible to happen and/or to have a moderate effect.
Moderate: likely to happen and/or to have serious effects.
Likely: almost sure to happen and/or to have a major effect.
Almost certain: sure to happen and/or have a major effect.
B. Impact (Consequence): The Y-axis determines the level of effects that the risk can cause.
Insignificant: won’t cause serious injuries or illnesses.
Minor: can cause injuries or illnesses, mild extent.
Significant: can cause injuries or illnesses, limited treatment.
Major: can cause irreversible injuries or illnesses, and medical attention.
Severe: can result in fatality.
Allocating a numeric value from 1 to 5, 1 being the lowest, against each category under Probability and Impact. To calculate the Risk Level, multiply the Probability value by the Impact value using the following formula:
Probability x Impact = Risk Level
Also, I am using the below guide for the numeric values for my analysis (figure 4)
Using a Probability and Impact Matrix
Since opportunities are evaluated like risks according to the probability impact grid, it makes sense to present both in the common chart which is called as the risk/opportunity matrix or mirror double probability.
Opportunities: In the risk/opportunity matrix or mirror double risk probability impact matrix, as shown in Figure 5, the opportunities are assessed on the right.
Threats: In the risk/opportunity matrix or mirror double risk probability and impact matrix as shown in Figure 5, the threats are assessed on the left.
Arrow of Attention: By placing Probability on the Y-axis and Impact on the X-axis, I urge readers to focus on the "Arrow of Attention," a triangular zone containing the most vital threats and opportunities that project managers and teams should prioritize. This helps in avoiding or minimizing threats and seizing opportunities.
Probability and Impact Matrix Pros and Cons
Now, let’s explore the advantages and disadvantages of employing a Probability and Impact Matrix, providing insights into its utility and potential limitations for risk assessment and management.
Pros
Identify event outcomes that need to be further investigated.
To identify where risk reduction can be possible.
Helps with prioritization of risks.
Focus decision-makers on the highest-priority risks
Present complex data in a Graphical representation of risks based on projects.
Cons
If any error happens in categorization this might lead to poor decision making.
They do not consider timescales and how risks may change over the years.
Low reliability of categorization since its subjective
Oversimplify the complexity or volatility of a risk.
Assessment of time frames not included (example: Factor shutdown in next two months might have different risk than shutdown for next 2 years)
Probability and Impact Matrix Template
There are many templates that are available for free online, and I always suggest my readers/mentees undergo detailed study on the subject by themselves or any course like PRINCE2 Foundation and Practitioner training. This has helped me to design various templates according to the requirements of the industry and projects.
Figure: 6 is one of my own templates (3X3) which I am using for various projects.
Probability and Impact Matrix Example
Let me explain about the Probability and Impact Matrix with a simple example.
My project is about the development of new glass doors for metro trains. During the planning stage, I did the risk analysis and found several risks which were then prioritized. The topmost risk was the availability of glasses for the doors. These glasses were specialized automotive specific and customized for this door design. Due to the complexity of the design, we ended up with only one supplier who could supply the same.
For this project, glass supplier delays are possible due to a lack of resources on their end, if a delay happens, the impact would be major because it would impact the entire project. I have categorized this risk as Medium – High based as shown in figure 7.
Conclusion
During my PMP® exam preparation, I discovered the significance of probability-impact risk analysis in project management. With the help of this article, I've shared my insights in a straightforward manner, elucidating the Probability and Impact Matrix with practical examples. Risks in projects can have positive or negative outcomes, and it's crucial for project managers to promptly identify and address them. Continuous learning is the key to success, and I strongly recommend considering KnowledgeHut's Project Management certification course for a comprehensive grasp of this vital domain.
Frequently Asked Questions (FAQs)
1. What is Probability Impact Risk Analysis?
Risk Probability: Determination of likelihood of a risk occurring and Impact Assessment: Evaluation of the impact of a risk if it occurs.
2. What are the 3 types of matrix in project management?
The three types of Matrixes in project management are Weak Matrix, Balanced Matrix and Strong Matrix.
3. What is impact used for?
Elimination or mitigation of risks that cause major impact to the project or product. Also understanding the impact of any action.
Arul Moses
Blog Author
Arul Moses Arulappan is a certified project management professional with exposure into automobile, energy, and elevator industries. He has a master’s in mechanical engineering from the university of Duisburg Essen, Germany. Started his career in research and development, he embarked upon a career as a project manager due to his passion. He is member of project management institute and volunteering as PMI south Asian champion.
Share This Article
Ready to Master the Skills that Drive Your Career?
Avail your free 1:1 mentorship session.
Upcoming Project Management Batches & Dates
Name
Date
Fee
Know more
Offer
Hello! Ready to elevate your career? Explore 500+ future-ready courses with KnowledgeHut upGrad 🚀x
1
Fast forward your career with 500+ future-ready courses ⏩💻👩🎓📚x