Explore Courses
course iconScrum AllianceCertified ScrumMaster (CSM) Certification
  • 16 Hours
Best seller
course iconScrum AllianceCertified Scrum Product Owner (CSPO) Certification
  • 16 Hours
Best seller
course iconScaled AgileLeading SAFe 6.0 Certification
  • 16 Hours
Trending
course iconScrum.orgProfessional Scrum Master (PSM) Certification
  • 16 Hours
course iconScaled AgileSAFe 6.0 Scrum Master (SSM) Certification
  • 16 Hours
course iconScaled Agile, Inc.Implementing SAFe 6.0 (SPC) Certification
  • 32 Hours
Recommended
course iconScaled Agile, Inc.SAFe 6.0 Release Train Engineer (RTE) Certification
  • 24 Hours
course iconScaled Agile, Inc.SAFe® 6.0 Product Owner/Product Manager (POPM)
  • 16 Hours
Trending
course iconKanban UniversityKMP I: Kanban System Design Course
  • 16 Hours
course iconIC AgileICP Agile Certified Coaching (ICP-ACC)
  • 24 Hours
course iconScrum.orgProfessional Scrum Product Owner I (PSPO I) Training
  • 16 Hours
course iconAgile Management Master's Program
  • 32 Hours
Trending
course iconAgile Excellence Master's Program
  • 32 Hours
Agile and ScrumScrum MasterProduct OwnerSAFe AgilistAgile CoachFull Stack Developer BootcampData Science BootcampCloud Masters BootcampReactNode JsKubernetesCertified Ethical HackingAWS Solutions Artchitct AssociateAzure Data Engineercourse iconPMIProject Management Professional (PMP) Certification
  • 36 Hours
Best seller
course iconAxelosPRINCE2 Foundation & Practitioner Certificationn
  • 32 Hours
course iconAxelosPRINCE2 Foundation Certification
  • 16 Hours
course iconAxelosPRINCE2 Practitioner Certification
  • 16 Hours
Change ManagementProject Management TechniquesCertified Associate in Project Management (CAPM) CertificationOracle Primavera P6 CertificationMicrosoft Projectcourse iconJob OrientedProject Management Master's Program
  • 45 Hours
Trending
course iconProject Management Master's Program
  • 45 Hours
Trending
PRINCE2 Practitioner CoursePRINCE2 Foundation CoursePMP® Exam PrepProject ManagerProgram Management ProfessionalPortfolio Management Professionalcourse iconAWSAWS Certified Solutions Architect - Associate
  • 32 Hours
Best seller
course iconAWSAWS Cloud Practitioner Certification
  • 32 Hours
course iconAWSAWS DevOps Certification
  • 24 Hours
course iconMicrosoftAzure Fundamentals Certification
  • 16 Hours
course iconMicrosoftAzure Administrator Certification
  • 24 Hours
Best seller
course iconMicrosoftAzure Data Engineer Certification
  • 45 Hours
Recommended
course iconMicrosoftAzure Solution Architect Certification
  • 32 Hours
course iconMicrosoftAzure Devops Certification
  • 40 Hours
course iconAWSSystems Operations on AWS Certification Training
  • 24 Hours
course iconAWSArchitecting on AWS
  • 32 Hours
course iconAWSDeveloping on AWS
  • 24 Hours
course iconJob OrientedAWS Cloud Architect Masters Program
  • 48 Hours
New
course iconCareer KickstarterCloud Engineer Bootcamp
  • 100 Hours
Trending
Cloud EngineerCloud ArchitectAWS Certified Developer Associate - Complete GuideAWS Certified DevOps EngineerAWS Certified Solutions Architect AssociateMicrosoft Certified Azure Data Engineer AssociateMicrosoft Azure Administrator (AZ-104) CourseAWS Certified SysOps Administrator AssociateMicrosoft Certified Azure Developer AssociateAWS Certified Cloud Practitionercourse iconAxelosITIL 4 Foundation Certification
  • 16 Hours
Best seller
course iconAxelosITIL Practitioner Certification
  • 16 Hours
course iconPeopleCertISO 14001 Foundation Certification
  • 16 Hours
course iconPeopleCertISO 20000 Certification
  • 16 Hours
course iconPeopleCertISO 27000 Foundation Certification
  • 24 Hours
course iconAxelosITIL 4 Specialist: Create, Deliver and Support Training
  • 24 Hours
course iconAxelosITIL 4 Specialist: Drive Stakeholder Value Training
  • 24 Hours
course iconAxelosITIL 4 Strategist Direct, Plan and Improve Training
  • 16 Hours
ITIL 4 Specialist: Create, Deliver and Support ExamITIL 4 Specialist: Drive Stakeholder Value (DSV) CourseITIL 4 Strategist: Direct, Plan, and ImproveITIL 4 Foundationcourse iconJob OrientedData Science Bootcamp
  • 6 Months
Trending
course iconJob OrientedData Engineer Bootcamp
  • 289 Hours
course iconJob OrientedData Analyst Bootcamp
  • 6 Months
course iconJob OrientedAI Engineer Bootcamp
  • 288 Hours
New
Data Science with PythonMachine Learning with PythonData Science with RMachine Learning with RPython for Data ScienceDeep Learning Certification TrainingNatural Language Processing (NLP)TensorflowSQL For Data Analyticscourse iconIIIT BangaloreExecutive PG Program in Data Science from IIIT-Bangalore
  • 12 Months
course iconMaryland UniversityExecutive PG Program in DS & ML
  • 12 Months
course iconMaryland UniversityCertificate Program in DS and BA
  • 31 Weeks
course iconIIIT BangaloreAdvanced Certificate Program in Data Science
  • 8+ Months
course iconLiverpool John Moores UniversityMaster of Science in ML and AI
  • 750+ Hours
course iconIIIT BangaloreExecutive PGP in ML and AI
  • 600+ Hours
Data ScientistData AnalystData EngineerAI EngineerData Analysis Using ExcelDeep Learning with Keras and TensorFlowDeployment of Machine Learning ModelsFundamentals of Reinforcement LearningIntroduction to Cutting-Edge AI with TransformersMachine Learning with PythonMaster Python: Advance Data Analysis with PythonMaths and Stats FoundationNatural Language Processing (NLP) with PythonPython for Data ScienceSQL for Data Analytics CoursesAI Advanced: Computer Vision for AI ProfessionalsMaster Applied Machine LearningMaster Time Series Forecasting Using Pythoncourse iconDevOps InstituteDevOps Foundation Certification
  • 16 Hours
Best seller
course iconCNCFCertified Kubernetes Administrator
  • 32 Hours
New
course iconDevops InstituteDevops Leader
  • 16 Hours
KubernetesDocker with KubernetesDockerJenkinsOpenstackAnsibleChefPuppetDevOps EngineerDevOps ExpertCI/CD with Jenkins XDevOps Using JenkinsCI-CD and DevOpsDocker & KubernetesDevOps Fundamentals Crash CourseMicrosoft Certified DevOps Engineer ExperteAnsible for Beginners: The Complete Crash CourseContainer Orchestration Using KubernetesContainerization Using DockerMaster Infrastructure Provisioning with Terraformcourse iconTableau Certification
  • 24 Hours
Recommended
course iconData Visualisation with Tableau Certification
  • 24 Hours
course iconMicrosoftMicrosoft Power BI Certification
  • 24 Hours
Best seller
course iconTIBCO Spotfire Training
  • 36 Hours
course iconData Visualization with QlikView Certification
  • 30 Hours
course iconSisense BI Certification
  • 16 Hours
Data Visualization Using Tableau TrainingData Analysis Using Excelcourse iconEC-CouncilCertified Ethical Hacker (CEH v12) Certification
  • 40 Hours
course iconISACACertified Information Systems Auditor (CISA) Certification
  • 22 Hours
course iconISACACertified Information Security Manager (CISM) Certification
  • 40 Hours
course icon(ISC)²Certified Information Systems Security Professional (CISSP)
  • 40 Hours
course icon(ISC)²Certified Cloud Security Professional (CCSP) Certification
  • 40 Hours
course iconCertified Information Privacy Professional - Europe (CIPP-E) Certification
  • 16 Hours
course iconISACACOBIT5 Foundation
  • 16 Hours
course iconPayment Card Industry Security Standards (PCI-DSS) Certification
  • 16 Hours
course iconIntroduction to Forensic
  • 40 Hours
course iconPurdue UniversityCybersecurity Certificate Program
  • 8 Months
CISSPcourse iconCareer KickstarterFull-Stack Developer Bootcamp
  • 6 Months
Best seller
course iconJob OrientedUI/UX Design Bootcamp
  • 3 Months
Best seller
course iconEnterprise RecommendedJava Full Stack Developer Bootcamp
  • 6 Months
course iconCareer KickstarterFront-End Development Bootcamp
  • 490+ Hours
course iconCareer AcceleratorBackend Development Bootcamp (Node JS)
  • 4 Months
ReactNode JSAngularJavascriptPHP and MySQLcourse iconPurdue UniversityCloud Back-End Development Certificate Program
  • 8 Months
course iconPurdue UniversityFull Stack Development Certificate Program
  • 9 Months
course iconIIIT BangaloreExecutive Post Graduate Program in Software Development - Specialisation in FSD
  • 13 Months
Angular TrainingBasics of Spring Core and MVCFront-End Development BootcampReact JS TrainingSpring Boot and Spring CloudMongoDB Developer Coursecourse iconBlockchain Professional Certification
  • 40 Hours
course iconBlockchain Solutions Architect Certification
  • 32 Hours
course iconBlockchain Security Engineer Certification
  • 32 Hours
course iconBlockchain Quality Engineer Certification
  • 24 Hours
course iconBlockchain 101 Certification
  • 5+ Hours
NFT Essentials 101: A Beginner's GuideIntroduction to DeFiPython CertificationAdvanced Python CourseR Programming LanguageAdvanced R CourseJavaJava Deep DiveScalaAdvanced ScalaC# TrainingMicrosoft .Net Frameworkcourse iconSalary Hike GuaranteedSoftware Engineer Interview Prep
  • 3 Months
Data Structures and Algorithms with JavaScriptData Structures and Algorithms with Java: The Practical GuideLinux Essentials for Developers: The Complete MasterclassMaster Git and GitHubMaster Java Programming LanguageProgramming Essentials for BeginnersComplete Python Programming CourseSoftware Engineering Fundamentals and Lifecycle (SEFLC) CourseTest-Driven Development for Java ProgrammersTypeScript: Beginner to Advanced

Critical Path Method in Project Management: How To Use It?

By Geetika Mathur

Updated on Oct 12, 2021 | 16 min read | 8.4k views

Share:

You can better visualize what steps need to be taken to accomplish your objective by creating a project plan. You're aided in doing it via the critical path method in project management. It is a method of project management that entails outlining the crucial actions that must be carried out to finish a project. By utilizing this method, you may manage work dependencies and establish reasonable deadlines. Learn how the critical route approach functions and how you can apply it to projects with your team by reading it. 

What is the Critical Path Method in Project Management?

The Critical Path Method (CPM) in project management is a straightforward but effective method for planning, scheduling, and assessing big, complicated projects. It is used to identify a project's critical path or the longest list of tasks that must be done before the entire project can be considered finished. 

Critical Path Analysis (CPA), another name for CPM, demonstrates how interdependent tasks are and which tasks are essential to a project. 

One of the key ideas in project management, and undoubtedly one of the most enduring, is the Critical Path Method (CPM). You may learn about the Critical Path Method and use it in your projects with the aid of this user-friendly technical project manager certification

CPM was created in the late 1950s to address the problem of rising costs brought on by ineffective scheduling. Since then, CPM in project management has gained popularity as a tool for organizing work and planning projects. It enables you to deconstruct challenging projects into manageable jobs and improves your comprehension of the project's flexibility. 

Critical Path Method and Critical Task

No matter how big or how expensive a project is, it must always complete a few fundamental duties. A task is deemed crucial if postponing it may delay the project's completion. Consider something basic like preparing pasta. 

The following would be a brief recipe for preparing pasta: 

  1. Boil pasta shells in salted water. 
  2. Heat a pan and add butter/oil when hot. 
  3. Add pasta and cook for some time. 

There are several other tasks you need to perform to make good pasta. Maybe add some vegetables and some cheese. Perhaps you could flip it on the other side, so the pasta is fully cooked through. 

But in addition to the recipe's three essential steps, these actions are also involved. You'll still have pasta even if you choose not to perform them. Even though it's not very excellent, pasta. 

The only thing you'll have, though, is a cold pan and raw pasta if you forget to boil the pasta or heat the pan. In other words, the three steps in the recipe outline the essential duties required to complete the project successfully and produce pasta. 

Master Right Skills & Boost Your Career

Avail your free 1:1 mentorship session

How to Find the Critical Path?  

By comparing the lengths of critical and non-critical tasks, one can identify the critical path. Examples of each stage are shown below.  

1. List your activities  

A work breakdown structure can be used to compile a list of all the project activities and tasks necessary to create the deliverables. The remainder of the CPM is built upon the list of activities in the WBS. 

As an illustration, suppose the education department is creating a fresh interactive blog article. These are some of the tasks that might be included in the WBS:  

Task ID Task Duration (in days)
A Draw up a plan 1
B Create a draft 3
C Edit the draft before submitting it. 2
D Graphics for design posts 5
E Visuals can be animated 2
F Put up articles 1

Starting to identify task dependencies is possible once you have a general understanding of everything that needs to be done. 

2. Identify Dependencies

Select the jobs that are interdependent based on your work breakdown structure. You can use this to find any job that can be completed concurrently with other tasks. 

Following the example from above, these job dependencies are: 

  • A is required for Task B. 
  • B is required for Task C. 
  • It is possible to simultaneously complete tasks C and D. 
  • D is required for Task E. 
  • C, D, and E all affect Task F. 

The critical path will be established using the list of dependent tasks, also known as an activity sequence. 

3. Create a network diagram  

The process of creating a network diagram, a flowchart that shows the sequence of events, using the work breakdown structure, is the next step. To show the dependencies between tasks, make a box for each one and add arrows to it. 

Prior to determining the overall project schedule, you will add additional time-bound components to the network diagram. 

4. Estimate task duration

You must first determine how long each activity will take to compute the critical path, which is the longest series of critical tasks. 

Try the following to gauge the time: 

  • Based on expertise and understanding, making intelligent assumptions 
  • Using data from earlier projects to estimate 
  • Using industry norms as a guide when estimating 

You could also attempt the forward pass and backwards pass method. 

5. Calculate the critical path

Even while it is possible to determine the critical path manually, it is faster to use a critical path algorithm. 

To determine the critical path manually, follow these steps: 

Step 1: For each activity, note the beginning and ending times. 

  • The duration of the first activity is its start time, which is 0, and its finish time. 
  • The prior activity's end time serves as the start time for the subsequent one, and its finish time is the sum of the two. 
  • For each activity, repeat the process. 

Step 2: To calculate the length of the complete sequence, look at the final activity's end time. 

Step 3: The critical path is the set of tasks that take the longest to complete. 

Here is how the critical path diagram may appear using the same example as above: 

The real project schedule can be constructed around the critical path after it has been identified. 

6. Calculate the float

A task's slack sometimes referred to as float, indicates how adaptable it is. It illustrates the amount of time that can be added to the task without influencing other tasks or the project's deadline for completion. 

Determining the float helps determine how flexible the project is. Use the resource known as a float to cover project risks or unforeseen problems. 

Since critical jobs have 0% float, their due dates are fixed. Positive float values designate tasks that belong on the non-critical path, where their postponement won't have an impact on when the project will be finished. Non-essential tasks could be skipped if time or resources are limited. 

It is possible to manually calculate the float or use an algorithm. To figure out the total float and free float, use the formulae from the section below. 

Total float vs. Free Float 

Total Float Free Float
This is the length of time that can pass since the early start date of activity without postponing the project's completion date or going against a schedule constraint. This refers to the maximum amount of time one activity can be postponed without negatively affecting the one after it. Free float is only possible when two or more actions have a single successor. This is where activities come together on a network diagram.
Total float = LS-ES or LF-EF. Free float = ES (next task) - EF (current task)

Project managers gain from having a thorough understanding of float for the following reasons: 

  • It ensures that projects finish on schedule: By allowing you to check the total float of a project to see if it is on schedule. Your chances of finishing early or on schedule increase with the size of the float. 
  • It lets you choose priorities: You'll have a better understanding of which chores should be given priority and which ones have more room for a postponement if you can identify the activities with free float. 
  • It's a helpful tool: Float is additional time that can be used to address project risks or unforeseen problems. You can decide how to use your float most effectively by being aware of how much of it you have. 

A Step-by-Step Process for Using Critical Path Method

CPM model in project management gives you insight into the status of your project and enables you to keep track of activities and their turnaround times. Here are some additional uses for CPM. 

Tighten up the timetables

Project deadlines might occasionally be pushed forwards, which is not ideal. The schedule compression methods of fast-tracking and crashing are both applicable under certain circumstances. 

  1. Fast tracking: Evaluate the critical path to identify tasks that can be carried out concurrently. The overall duration will decrease as more parallel processes are run. 
  2. Increasing resources is a step in the process of "crashing" operations. Make sure the additional resources will still fit inside the project's scope before acquiring them and inform the stakeholders of any modifications. 

Having the critical path diagram can aid in selecting the best tactic to fulfil revised deadlines. 

Overcome a lack of resources

Remember that the CPM method in project management does not account for resource availability. You can employ resource leveling approaches to address resource issues, such as a team member who is overbooked or lacks equipment. 

These strategies are meant to address resource overallocation problems and guarantee that a project can be finished with the resources that are currently on hand. 

Resource levelling affects project start and end dates, thus you might need to modify the critical route or use this method for activities that have floated. 

Gather information for later use

Since you're working with informed estimations for activity durations, the schedule generated by CPM in software project management is liable to alter. As the project progresses, you can contrast the original critical path with the current critical path. 

Future studies can utilize this information as a guide to predict work durations more precisely. 

Critical path method example: 

  1. Reduce delays: By determining the most crucial order of work for a project using the Critical Path Method. Employing this knowledge, managers can streamline tasks along the crucial path to cut down on delays. 
  2. Create a visual representation of dependencies: The CPM relies on a list of all project-related tasks and their dependents. You may visualize all dependencies and order tasks in accordance with the chart you've made. 
  3. Organize better: The CPM aids in the division of work into sequences and deliverables into sequences in complex projects. Project organization is much enhanced by doing this, as well as focusing on visualizing dependencies, mapping constraints, and establishing the essential route of tasks. 
  4. Enhance productivity: Project managers can better understand the significance of each work by mapping the critical route. By adding or withdrawing resources according to the significance of the work, they can more effectively distribute resources. 
  5. Calculating the float: The float describes how much work can be postponed without having an adverse effect on the project schedule, as we'll see later. This plays a significant role in the Critical Path Method. You can allocate resources more skillfully by computing the float. 

Key Terms in Critical Path Method 

It’s important to understand and get up-to-speed with the terms that are used by project managers who are working on this method. Here’s a ready reckoner:  

  1. Schedule refers to the entire roster of activities that are a part of the project along with the time it takes to finish each activity.  
  2. Duration is the estimated time it takes to complete a particular activity.  
  3. Activity-On-Node (AON) is a visual representation of the schedule showing how activities are linked to each other.  
  4. Critical path is the longest chain of activities in the project.  
  5. Critical Activity is any activity on the critical path. The activity is considered critical because a delay in that activity will cause a delay in project completion.  
  6. Early Start (ES) is the earliest date a particular activity can be started on.  
  7. Early Finish (EF) is the earliest date an activity can be completed on.  
  8. Lag is the estimated time to wait before an activity can start.   
  9. Late Start (LS) is the latest date the activity needs to be started by, without delaying the project completion.   
  10. Late Finish (LF) is the date an activity needs to be finished by, without delaying the project.   
  11. Predecessor is an activity that precedes the current activity.  
  12. Successor is the activity that comes right after the completion of the current activity.  
  13. Free Float (FF) is the maximum number of days an activity can be delayed, without delaying a succeeding activity.  
  14. Total Float (TF) is the maximum number of days an activity can be delayed, without causing a delay in the project completion date. 

Become a project management expert with best PRINCE2 course. Take control of your projects and achieve unprecedented success!

Importance of Critical Path Method 

Critical Path Method is a tried and tested way of managing projects. It has been in use for over 60 years, and has been proven to help project managers to smoothen workflows, ironing out any obstacles to progress. helps project managers to:  

  • Prioritize activities  
  • Identify activities that can run simultaneously  
  • Optimize resource allocation  
  • Track progress in real time  
  • Comply with deadlines  
  • Simplify dependencies  
  • Get a wide, bird’s-eye perspective on all project activities 

Top Cities where Knowledgehut Conduct Project Management Certification Training Course Online

Project Management Courses in London Project Management Courses in Singapore
Project Management Courses in Melbourne Project Management Courses in Toronto
Project Management Courses in Sydney Project Management Courses in Perth
Project Management Courses in Bangalore Project Management Courses in Dubai
Project Management Courses in Mumbai Project Management Courses in Brisbane

Tools and Software to Calculate Critical Path

There are a few tools or methods that are popularly used to find the Critical Path in a project.   

Activity On Node (AON):

Is a method that represents activities in a diagram to show interdependencies between them. Once durations, early start date, and early finish date are assigned, the critical path can be mapped by using the earliest start date for each activity. This technique is called Forward Pass.   

Using the Latest Start date and Latest Finish Date and starting from project completion, you can calculate the critical path through a similar technique called Backward pass.  

GANTT: 

Charts are used for simpler projects where activities are represented in a bar chart format instead of a network chart. This is an alternate method of finding the critical path in a project.  

PERT or Program Evaluation and Review Technique:

Works based on a similar principle to other methods. It dismisses the notion that there is a fixed amount of time for an activity to be completed. Instead, it estimates a best-case scenario, worst-case scenario, and an ordinary scenario to estimate the amount of time each activity takes. It calculates variance and standard deviation to see which activities are likely to risk delaying the project by exceeding the time they are estimated to take.   

PERT is a more dynamic method that is more suitable to make flexible project plans as it accounts for the fact that time taken for activities cannot be estimated or predicted accurately. 

Software for calculating Critical Path

The calculations can seem complex and if done manually it may end up being a time-consuming exercise. Thankfully, project management software come with options to calculate the critical path.  

MS Project, Wrike, Capterra, Mavenlink, Buildertrend, and WorkflowMax, among others, have features that help the user to identify and monitor the critical path in their projects and keep an eye on activities that are nearing the maximum delay, threatening to derail the project deliveries. 

Conclusion

Planning activities and managing resources are two areas where CPM can be an advantage in project management. You will find it simple to make timetables and keep track of tasks with the aid of project planning tools. You can learn more on PMP certification course online and get certified through KnowledgeHut project management trainings

Frequently Asked Questions (FAQs)

1. What is critical path method example?

2. What is the critical path formula?

3. What is the importance of critical path method in project planning?

4. What is the purpose of critical path?

5. What are the benefits of critical path method?

Geetika Mathur

Geetika Mathur

11 articles published

Get Free Consultation

By submitting, I accept the T&C and
Privacy Policy