PERT (Program Evaluation Review Technique) is an estimation technique that was first developed and applied by the United States Defence establishment for their Ballistic Missile development program. It was one of their most ambitious programs. Completion of this in time ahead of the other nations was critical for them. Such a missile development program was filled with a huge amount of uncertainty, as it required a large number of supplier agencies working on new technology development. This method of estimation helped them build in all the uncertainties in their estimates and helped them to complete this program ahead of their expected schedule.
The PERT estimation technique (Program Evaluation Review Technique) formula is a cornerstone of the three-point estimation method, designed to handle the uncertainties inherent in project tasks. It uses three types of estimates:
O (Optimistic Estimate): The shortest possible time required to complete the task, assuming everything proceeds better than is typically expected.
M (Most Likely Estimate): The best estimate of the duration required to complete the task, assuming everything goes as normal.
P (Pessimistic Estimate): The logest time that might be taken to complete the task, assuming everything goes wrong.
The formula to calculate the Expected Time (TE) is:
TE= (O+4*M+P)/6
This formula not only calculates an average of the estimates but gives the most weight to the most likely outcome, making it a robust tool for project managers.
Consider a project task of designing a website. The optimistic time to complete the design is 10 days, the most likely time is 15 days, and the pessimistic time is 25 days. Using the PERT formula, the expected time (TE) would be calculated as follows:
TE= (10+4*15+25)/6=(10+60+25)/6=95/6≈15.83
The three estimates in PERT represent the three chances or scenarios under which a project might unfold:
The PERT estimation technique involves several key steps:
Using PERT estimation technique offers several benefits:
Pros:
Cons:
Pitfalls:
By understanding and applying these elements of PERT, project managers can enhance their planning effectiveness and increase the likelihood of project success.
PERT estimation technique will be a practical approach for estimating when the tasks on hand are filled with uncertainties, where the tasks may take up different estimates depending upon certain conditions. Project management professional certification is a perfect way to learn this technique while preparing. The actual estimate is dependent on certain variables. PERT allows the preparation of a more practical estimate by factoring the 3-point estimates into one as explained above.
A valuable piece of knowledge. Thank you!
This blog is appreciated, thanks.
I like the article. Thank you very much.
Thank you for the information.
The content of the motivation theories are well explained and its has been of great help to me . Thank you for making it that easy for easy understanding.
Leave a Reply
Your email address will not be published. Required fields are marked *