top
upGrad KnowledgeHut SkillFest Sale!

Search

Project Management Tutorial

Scheduling is the process of sequencing all the project activities by assigning each activity a duration in a way so that they are completed in a timely manner. Critical Path Method (CPM) is the most widely adopted method of scheduling. In spite of preparing an optimized schedule and building adequate buffers into activities, it has been very often found that the projects miss their committed schedule. Schedule overruns have become the norm.  As per the latest survey of PMI pulse of the Profession 2017, only 50% of the projects completed on time.This is when Dr Eliyahu M Goldratt studied the underlying reasons of failing schedule commitments, proposed a different method of scheduling known as Critical Chain Method. Dr Goldratt studied deeply the reasons of project failure, specially the failure in scheduling point of view. He found that most of the reasons are due to human behaviour and cultural beliefs of people. Below are some of the reasons for project delays.Over-estimatingOverrunning the estimateNot passing on time savingsPath convergenceMultitaskingLoss of focus1. Causes of Over-Estimating:Estimate criteria not well-definedLevel of Accuracy?Probability of completion within estimate?Contingency included?Optimistic?  Pessimistic? Most Likely?Any instructions about “buffer” or “padding”Cultural beliefs“PM wants ‘low risk’ estimate”Organizational policiesRewards for on-time, punishment for lateAdjustments to schedules2. Causes of Overrunning the Estimate:Tendency to wait until activity is urgent to work on itWillingness to accept other high priority work due to belief that contingency is built into estimateTypical work pattern of many people“Student Syndrome” – GoldrattWork expands to fill the time—and “safety time is wasted” (Parkinson’s Law)Failure to provide resources when needed3. Causes of Not Passing on Time Savings:Little or no reward for finishing earlyFinish early one time and it’s always expectedFinish early, get more to do!Time & Materials Contracts — early finish = less revenueResult:Completion is made a lower priority  Contingency Time that was in the estimate was wasted! 4. What is Path Convergence?Multiple predecessors merging into a single activityWhat’s the result of Path Convergence?The longest delay is passed on to the successor activity 5. Causes of Multitasking:Trying to keep everyone busy“While waiting, work on something else”Many companies encourage extensive multitaskingFocus on local efficiency could damage overall performance of a system (Sub-optimization) 6. Causes of Loss of Focus:Early Start SchedulesAllow all activity pathways to start at same timeCan cause PM’s attention to become diffusedChanging Critical Path during project performanceTrying to exclusively use Earned Value for project controlEV does not discriminate between activities of differing importanceUsing Earned Value Action Thresholds that are too tightResulting in too many control actionsCritical Chain Method of SchedulingA Critical Chain is a resource constrained critical path. Scheduling in the new method is done by keeping the above problems in mind and ensuring that we turn them into an advantage. In critical chain method, The team members are encouraged to make optimistic estimates rather than traditional pessimistic estimates Buffers are not kept with individual activities, rather than the collective buffers are built at the end of each path, in this case known as a chain of activities. Project Buffer is kept at the end of the Critical Chain (longest chain) and Feeding Buffers are kept at the end of Non-Critical Chains which are feeding into the Critical Chain thus reducing the impact of Path Convergence impacts.Buffers are shown as activities which are under the control of the project manager.This helps in effective use of buffers and eliminating their unnecessary wastage. Resources are not punished if they miss a deadline of an activity, as there are buffer at the end of the chainsLate Start schedules are used rather than traditional Early Start schedules used in Critical Path MethodResources are allocated 100% to avoid multitasking.A conceptual example of critical chain scheduling using buffers at the end of chain is shown below.The steps followed are as below:Both pessimistic and optimistic estimates are taken from the team members for each task.In above example, tasks A,B and C have pessimistic estimate of 4 weeks each and an optimistic estimate of 2 weeks each.First a low-risk schedule with pessimistic estimates is built. In this case it comes to 12 weeks.Then the critical chain schedule is prepared by taking the optimistic estimates, which comes to 6 weeks. Then the 2 weeks savings from each task is used as a buffer for the whole chain.Fifty per cent of the 6 weeks, which is 3 weeks, is added as buffer at the end of the chain.The total duration of the chain now comes to 9 weeks with a project buffer of 3 weeks.The resources are encouraged to complete the tasks in the optimistic time. In case someone fails, they are not punished. The project buffer, which is now under the control of project manager, can be responsibly used as the cushion. Conclusion:The Critical Chain Method has practically addressed the challenges in standard scheduling using critical path method. And CCM effectively comes out as a better method and has significantly improved the chances of meeting a schedule deadline. This method is being practiced across organizations, both in projects as well as operation scheduling. Take online PMP certification on KnowledgeHut.
logo

Project Management Tutorial

Critical Chain Method

Scheduling is the process of sequencing all the project activities by assigning each activity a duration in a way so that they are completed in a timely manner. Critical Path Method (CPM) is the most widely adopted method of scheduling. 

In spite of preparing an optimized schedule and building adequate buffers into activities, it has been very often found that the projects miss their committed schedule. Schedule overruns have become the norm.  As per the latest survey of PMI pulse of the Profession 2017, only 50% of the projects completed on time.

This is when Dr Eliyahu M Goldratt studied the underlying reasons of failing schedule commitments, proposed a different method of scheduling known as Critical Chain Method. 

Dr Goldratt studied deeply the reasons of project failure, specially the failure in scheduling point of view. He found that most of the reasons are due to human behaviour and cultural beliefs of people. Below are some of the reasons for project delays.

  1. Over-estimating
  2. Overrunning the estimate
  3. Not passing on time savings
  4. Path convergence
  5. Multitasking
  6. Loss of focus

1. Causes of Over-Estimating:

  • Estimate criteria not well-defined
    • Level of Accuracy?
    • Probability of completion within estimate?
  • Contingency included?
    • Optimistic?  Pessimistic? Most Likely?
    • Any instructions about “buffer” or “padding”
  • Cultural beliefs
    • “PM wants ‘low risk’ estimate”
  • Organizational policies
    • Rewards for on-time, punishment for late
    • Adjustments to schedules

2. Causes of Overrunning the Estimate:

  • Tendency to wait until activity is urgent to work on it
  • Willingness to accept other high priority work due to belief that contingency is built into estimate
  • Typical work pattern of many people
    • “Student Syndrome” – Goldratt
    • Work expands to fill the time—and “safety time is wasted” (Parkinson’s Law)
  • Failure to provide resources when needed

3. Causes of Not Passing on Time Savings:

  • Little or no reward for finishing early
  • Finish early one time and it’s always expected
  • Finish early, get more to do!
  • Time & Materials Contracts — early finish = less revenue
  • Result:
    • Completion is made a lower priority  
    • Contingency Time that was in the estimate was wasted!

 4. What is Path Convergence?

  • Multiple predecessors merging into a single activity
  • What’s the result of Path Convergence?
    • The longest delay is passed on to the successor activity

 5. Causes of Multitasking:

  • Trying to keep everyone busy
    • “While waiting, work on something else”
    • Many companies encourage extensive multitasking
  • Focus on local efficiency could damage overall performance of a system (Sub-optimization)

 6Causes of Loss of Focus:

  • Early Start Schedules
    • Allow all activity pathways to start at same time
    • Can cause PM’s attention to become diffused
  • Changing Critical Path during project performance
  • Trying to exclusively use Earned Value for project control
    • EV does not discriminate between activities of differing importance
  • Using Earned Value Action Thresholds that are too tight
    • Resulting in too many control actions

Critical Chain Method of Scheduling

A Critical Chain is a resource constrained critical path. Scheduling in the new method is done by keeping the above problems in mind and ensuring that we turn them into an advantage. 

In critical chain method, 

  1. The team members are encouraged to make optimistic estimates rather than traditional pessimistic estimates 
  2. Buffers are not kept with individual activities, rather than the collective buffers are built at the end of each path, in this case known as a chain of activities. 
  3. Project Buffer is kept at the end of the Critical Chain (longest chain) and Feeding Buffers are kept at the end of Non-Critical Chains which are feeding into the Critical Chain thus reducing the impact of Path Convergence impacts.
  4. Buffers are shown as activities which are under the control of the project manager.
  5. This helps in effective use of buffers and eliminating their unnecessary wastage. 
  6. Resources are not punished if they miss a deadline of an activity, as there are buffer at the end of the chains
  7. Late Start schedules are used rather than traditional Early Start schedules used in Critical Path Method
  8. Resources are allocated 100% to avoid multitasking.

A conceptual example of critical chain scheduling using buffers at the end of chain is shown below.

critical chain scheduling using buffersThe steps followed are as below:

  1. Both pessimistic and optimistic estimates are taken from the team members for each task.
  2. In above example, tasks A,B and C have pessimistic estimate of 4 weeks each and an optimistic estimate of 2 weeks each.
  3. First a low-risk schedule with pessimistic estimates is built. In this case it comes to 12 weeks.
  4. Then the critical chain schedule is prepared by taking the optimistic estimates, which comes to 6 weeks. Then the 2 weeks savings from each task is used as a buffer for the whole chain.
  5. Fifty per cent of the 6 weeks, which is 3 weeks, is added as buffer at the end of the chain.
  6. The total duration of the chain now comes to 9 weeks with a project buffer of 3 weeks.
  7. The resources are encouraged to complete the tasks in the optimistic time. In case someone fails, they are not punished. The project buffer, which is now under the control of project manager, can be responsibly used as the cushion. 

Conclusion:

The Critical Chain Method has practically addressed the challenges in standard scheduling using critical path method. And CCM effectively comes out as a better method and has significantly improved the chances of meeting a schedule deadline. This method is being practiced across organizations, both in projects as well as operation scheduling. Take online PMP certification on KnowledgeHut.

Leave a Reply

Your email address will not be published. Required fields are marked *

Comments

Haya

A valuable piece of knowledge. Thank you!

Eniola Samson

This blog is appreciated, thanks.

Lydia

I like the article. Thank you very much.

Emmy

Thank you for the information.

Luke

The content of the motivation theories are well explained and its has been of great help to me . Thank you for making it that easy for easy understanding.

Suggested Tutorials

PRINCE2 Tutorial [Video]

PRINCE2 Tutorial [Video]

USEFUL LINKS